We just got informed by HHLA (Hamburg Hafen und Logistik AG) that due to maintenance works by ATLAS there won´t be any electronic releases (RLSinfo) upon Z-numbers possible on Saturday, 10th of March 2012 in the period between 7 a.m. and 12 p.m. Affected by this measurement of the customs are all ATLAS-participants in …
We just got informed by HHLA (Hamburger Hafen und Logistik AG) that due to a very high workload a dispatch of containers at the HHLA terminal Burchardkai (CTB) cannot be guaranteed for today.
We have to inform You, that severe storms over Germany causes delays in rail traffic. Some Terminals stopped their loading/unloading activities. Due to the storm partially damages of overhead lines causes.
Because of a severe storm, the port of Rotterdam did temporarily stop all loading/unloading processes for vessels, trains and trucks at all terminals. We are currently verifying if a departure with a 24 hrs delay will be possible. Further information as soon as available.
Due to the re-arrangement of the Swiss Split by Swiss Railways (SBB Cargo AG) we have published for this service from/to the terminals Rekingen (AG) and Frenkendorf (BL) a new and individual offer for each terminal.
After a long period of set-up time, we are pleased to inform you that we now may offer you, besides our Rotterdam – Switzerland service (Rhine-Shuttle), the new Swiss-Hansa-Shuttle as a direct combined traffic connection on the following lines as from December 14, 2011. » Hamburg CTA – Frenkendorf CT and v.v. » Hamburg …
Because of high traffic volume, we decided to operate an extra train between Rotterdam and Switzerland. Departure Rotterdam on Monday Dec. 5 to Frenkendorf Terminal.
In the coming month of December 2011, a CAF will be applied as is did in this ending month (no CAF appliance for transports with the Rhine Shuttle from/to Frenkendorf). Due to a still stable currency fluctuation the CAF remains unchanged for the upcoming month.
We just got informed by Eurokombi in Hamburg that due to asphalting works of the complete Antwerpenstrasse relocations of empty units cannot be done from and to depot Dradenau in the period between 26th and 28th of November 2011.
We just got by HPA (Hamburg Port Authority) that due to the discovery of a bomb (track 403) in the port of Hamburg the connections HP, CTA, Kühne & Nagel and Rhenus Log. as well as Abstellgruppe Altenwerder East are not reachable today.